Summer Lot Maintenance Schedule: (reflowed for weather)
Date |
Location |
Type of work |
Monday Aug 6 | Brooks St & Wake Dr | Space Striping |
Monday Aug 6 | Plant Lot | Milling |
Tuesday Aug 7 | Plant Lot | Repave 1/2 of lot & Stripe |
Tuesday Aug 7 | Zable Stadium Lot | Milling |
Wednesday Aug 8 | Plant Lot | Repave remaining 1/2 & Stripe |
Wednesday Aug 8 | Zable Stadium Lot | Repave 1/2 of lot & Stripe |
Thursday Aug 9 | Zable Stadium Lot | Repave remaining 1/2 & Stripe |
Friday Aug 10 | School of Ed Lot 6 & 7 | Mill, Repave, Sealcoat & Stripe |
Friday Aug 10 | Grigsby Dr & Procurement Parking | Sidewalk & Space Striping |
During the large milling operations paving contractors will at their discretion allow vehicles to pass through the areas, please exercise caution and await instructions from flagmen onsite.
During the Plant lot paving faculty & staff should find parking in the nearby Law School lots, those in the vicinity of the Zable Stadium may park in the OTP Red Garage or rear OTP lot. Please be mindful of the height restrictions in the Red Garage. Vans, Pick-up trucks, Large SUVs must use the rear lot.