Summer Parking Lot Maintenance

Summary

Updated Friday Aug 3rd - Several campus lots and parking areas will be fully or partially closed for paving and maintenance, every effort has been made to minimize displacement. See schedule below for details and list of areas.

Full Description

Summer Lot Maintenance Schedule: (reflowed for weather)

Date 
Location
Type of work
Monday Aug 6 Brooks St & Wake Dr Space Striping
Monday Aug 6  Plant Lot Milling 
Tuesday Aug 7 Plant Lot  Repave 1/2 of lot & Stripe 
Tuesday Aug 7 Zable Stadium Lot Milling
Wednesday Aug 8 Plant Lot Repave remaining 1/2 & Stripe
Wednesday Aug 8 Zable Stadium Lot Repave 1/2 of lot & Stripe
Thursday Aug 9 Zable Stadium Lot Repave remaining 1/2 & Stripe
Friday Aug 10 School of Ed Lot 6 & 7 Mill, Repave, Sealcoat & Stripe 
Friday Aug 10 Grigsby Dr & Procurement Parking Sidewalk & Space Striping

During the large milling operations paving contractors will at their discretion allow vehicles to pass through the areas, please exercise caution and await instructions from flagmen onsite. 

During the Plant lot paving faculty & staff should find parking in the nearby Law School lots, those in the vicinity of the Zable Stadium may park in the OTP Red Garage or rear OTP lot. Please be mindful of the height restrictions in the Red Garage. Vans, Pick-up trucks, Large SUVs must use the rear lot.