Sadler West - Temporary Road Closure Plans
Summary
Mar 5th - Jul 5th, 2022
Full Description
Effective Saturday Mar 5th, the connective road from the rear Sadler Center parking lot to the Sadler Center terrace will be closed to all traffic, including pedestrians. Detours and signage will be in place and posted to guide you around the construction project for the duration of the closure through Jul 2022. The work schedule is listed below:- Road Closure - March 5th
- Start Site Work – March 7th (6 Weeks) Complete April 15th
o Remove soils to subgrade
o Place new stone
o Replace rocks and planting
o Pour Sub slabs and curb and gutter
o Install top soil - Start Brick Pavers May 16th
- Complete Store Fronts and Metal Cladding May 20th
- Click here to download a pdf rendering of the Future Student Life Walk
Area map, pedestrian detour is shown as a red line.