End of Summer Parking Lot Maintenance
Summary
As of: Wednesday Aug 14th, 2024
Full Description
Schedule adjusted due to recent inclement weather
The below is confirmed as of 8/14/24 and will be posted accordingly:
Wednesday 8/14 - Full milling, repaving & striping
- Grad Complex Overflow Lot
Friday 8/16 - Seal Coat & stripe
- Richmond Hall
Saturday 8/17 – Sealcoat and striping
- Dawson Circle
- Law School Circle & Law F/S Lot 1
Monday 8/19 - Full paving & striping
- Camm Lot & Patch Fire Lane at OTP
- Dillard Complex
All lots need to be fully cleared of all cars on each of the above dates. Ticketing and towing will be in effect by 7 am each day.