Plumeri Baseball Practice Facility

The project will construct a single story 5,280 gsf indoor baseball training facility along the third base line of Plumeri Park.  The pre-engineered building will enclose three batting tunnels and a soft pitch "on deck" area within an all-weather envelope.

  • Project Number:  0197-001-13
  • Cost: $ 1,063,700.00
  • Fund Source: Private (0302)(PRF-Athletics)
  • Renovation/additional GSF: approx. 5280
  • Start Date: Aug 2013
  • Finish Date:  Apr 2016
  • Project ManagerOot Singhaseni
  • Design Team:  CHA Consulting, Inc.
  • Contractor:  A.R. Chesson Construction
  • Progress: Completed