Music Arts Center

Design and construction of Phase 1 of the Arts Quarter for the Music Department consists of 74,951 gross square feet of new teaching and performance space. Key program elements include four classrooms/seminar rooms, 15 teaching studios, 33 practice rooms, 60 person choral and 45 person instrumental practice rooms, a 125 seat recital hall and a 450 seat recital hall. All space will be uniquely suited to the instructional and acoustic needs of the Music program.

Project Details
  • Project Number: 204 – 18292
  • Cost: $138,850,000  (Budget inclusive of Music Arts Center and PBK Hall projects)
  • Fund Source: State
  • New Construction GSF: 74,951 gsf
  • Project Start Date: Feb 2017
  • Construction Start Date : Jun 2019
  • Finish Date: August 2023
  • Project Manager: Catherine Parker
  • Design Team: Moseley/HGA
  • Contractor: Whiting Turner
Building Committee

Abby Houser, Associate Budget Director
Amy Sebring
, Chief Operating Officer
Arthur Knight
, Associate Committee Chair, Arts & Sciences
Catherine Parker
, Project Manager
Christopher Owens, Arts & Sciences
Eric Bradley, Committee Chair, Arts & Sciences
Jackie Ferree, Associate Vice President for Business Services
Jamie Bartlett, Arts & Sciences
Laurie Wolf, Arts & Sciences
Martha Terrell, Assistant to the VP for Finance & Administration
Sam Jones, Senior Vice President for Finance & Administration
Van Dobson / Sam Hayes
, Chief Facilities Officer

The Music Arts Center's Concert Hall, photo by HGA