Monroe Hall Renovations
This project renovated a 37,732 square foot residence hall, providing upgraded infrastructure, new windows, roof system upgrades, new interior and exterior doors, new HVAC system, new plumbing pipes and fixtures, new electrical and fire protection systems, and new interior finishes throughout the building. Additional common spaces were created, and the building now includes ADA compliant features that include a new elevator and accessible entrances. Abatement of all hazardous materials was included, and the design features various sustainability initiatives, including the first operational geothermal wells on the William & Mary campus.
Housing & Dining Comprehensive Facilities Plan
Project Details
- Cost: $22,100,000
- Fund Source: W&M Bonds
- Renovation GSF: 37,732
- Project Start Date: Oct 2020
- Construction Start Date: June 2023
- Finish Date: Aug 2024
- Project Manager: Adam Witkowski
- Design Team: VDMO Architects
- Contractor (CM): Kjellstrom+Lee
Building Committee
Abby Houser, Associate Budget Director
Adam Witkowski, Project Manager
Chris Durden, Director of Business Operations, Res Life
Dan Pisaniello, University Architect
Sam Hayes, Chief Facilities Officer
Ginger Ambler, Vice President for Student Affairs
Maggie Evans, Associate Vice President for Student Affairs