Dillard Soccer Field Revision
The scope of this project includes:
Prepare a master plan design for the overall site
Add lighting for the field
Add scoreboard for the field
Add Ballstop Netting
Add a 12'x20' prefab storage building
- Project Name: Dillard Soccer Field Revision
- Project Number: 270030
- Cost: $1,013,000
- Fund Source:
- Renovation/additional GSF: 2,300
- Project Start Date: 02/17/20
- Construction Start Date: 06/07/21
- Finish Date: 08/31/21
- Project Manager: Catherine Parker
- Design Team: Draper Aden Associates
- Contractor: FieldTurf