Jill Ellis Field

The design and construct of an additional practice field and associated infrastructure at the Dillard Complex was completed as a collaborative effort between Athletics and Campus Recreation. This project was privately funded and was dedicated as Jill Ellis Field, establishing the 1987 Women's Soccer Team Training Center.

  • Project Number:  204-80003
  • Cost: $2,300,000
  • Fund Source: Private Funds
  • Project Start Date: January 2023
  • Construction Start Date: January 2024
  • Finish Date:  April 2024
  • Project Manager: Catherine Parker (Design) / Anne Baskerville (Construction)
  • Design Team: TRC Companies, Inc.
  • Contractor: GTR Turf, Inc.
Building Committee

Catherine Parker/Anne Baskerville, Project Manager
Dan Pisaniello, University Architect
Linda Knight, Director of Campus Recreation
Richard Whitmore, Deputy Director of Athletics