Brafferton and Brafferton Kitchen (Renovation)
The project renews building systems within the Brafferton and Brafferton kitchen. The project will seal the exterior envelope (roof, windows, foundation), installl state of the art builidng systems (HVAC, Fire systems, HA access), and restore affected building fabric.
- Cost: $3.4-million
- Fund Source: Private/VCBA Funds
- Renovation GSF: 6,711
- Start Date: July 2012
- Finish Date: July 2013
- Design Team: GWWO
- Contractor: Virtexco
- Progress: A ceremony was held on Friday, November 22, 2013 to celebrate the Brafferton's renewal.