Blow IT Data Center Renovation
Scope – Install new HVAC system for computer rack cooling to correct the hot and cold aisle air mixing; install redundant power sources - two electrical buses (A&B) for scalability and ease of maintenance: and, for uninterruptible power supply, two new UPSs will be installed and backed up by a new generator power source. The generator is sized to handle the loads currently on the existing generator.
- Project Number: 204-18112-003 -- DEB PC# 204-A9204-005
- Cost: $ 2,710,000
- Fund Source: Debt (0815)
- Renovation/additional GSF: 56, 000
- Start Date: Mar 2017
- Construction Start Date: July 2021
- Finish Date: Dec 2022
- Project Manager: Adam Witkowski
- Design Team: Clark Nexsen
- Contractor: Facility Support, Inc.