Close menu Resources for... William & Mary
W&M menu close William & Mary

Adair Hall Elevator & Restroom Renovations

The project supports a study, design, and construction to examine and improve accessibility issues at facilities not currently targeted for renovation within the next decade, and/or improvements to various campus locations that impede accessibility. This particular project added an elevator and renovated public restrooms to meet ADA standards. 

  • Project Number:  204-18002-01
  • Cost: $ 2,207,395
  • Fund Source:  Virginia College Building Authority
  • Renovation/additional GSF:  1812
  • Start Date:  Jan 2013
  • Finish Date:  Sep 2018
  • Project Manager Ben Mulherin
  • Design Team: Clark Nexson
  • Contractor:  J.W. Enoch
  • Progress: Completed